“Test 990, IBM WebSphere Bus Modeler Adv V6.0, Bus Anl+Design”, also known as 000-990 exam, is a IBM certification. With the complete collection of questions and answers, Pass4sure has assembled to take you through 128 Q&A to your 000-990 Exam preparation. In the 000-990 exam resources, you will cover every field and category in IBM certifications helping to ready you for your successful IBM Certification.
Exam Details
This certification is intended for an intermediate-level business analyst who designs business models and processes. This professional observes real life processes and gathers information to create business process models. They perform organization and resource modeling, analyze processes considering a variety of dimensions, build accurate and realistic simulations, create reports, and build business measures to address productivity and performance management. This certification applies to business analysts who use IBM WebSphere Business Modeler Advanced V6.0 for process modeling, analysis, simulation, and reporting. These individuals have developed skills in Business Process Management (BPM) and Business Activities Management (BAM) practices. It is expected that this individual will be generally self-sufficient and able to perform the tasks involved in the role with limited assistance from peers, product documentation and vendor support services. To attain the IBM Certified Business Process Analyst – WebSphere Business Modeler Advanced V6.0 certification, candidates must pass 1 test 000-990. To prepare for this test, based on the job role and test objectives, refer to the Recommended educational resources under Core Requirements below.
000-990
QUESTION 1
A business analyst is asked to create a training manual for new employees, and this training manual will show the sequence of steps within its business process, and the relationships of a process to other sub-processes. Which of the following predefined reports should be used?
A. Process specification report
B. Process summary report
C. Process details report
D. Process procedure report
Answer: D
QUESTION 2
A sales manager needs to be alerted when the average sales order goes below a target value of $100. How can this be accomplished?
A. Create a sales order total metric for each order process instance. Create a KPI based
on the metrics average. Generate a situation event and attach it to the KPI, giving it a unique name. Set up a condition in the situation event to send the event when the sales average dips below $100.
B. Create a sales order total metric for each order process instance. Develop an aggregate metric which averages these totals. Create a KPI based on the aggregate metric. Generate
a situation event and attach it to the sales order total metric, giving it a unique name. Set
up a condition in the situation event to send the event when the sales average dips below
$100.
C. Create a sales order total metric for each order process instance. Develop an aggregate metric which averages these totals. Create a KPI based on the aggregate metric. Generate
a situation event and attach it to the aggregate metric, giving it a unique name. Set up a condition in the situation event to send the event when the sales average dips below $100.
D. Create a sales order total metric for each order process instance. Create a KPI based
on the metrics average. Generate a situation event and attach it to the metric, giving it a unique name. Set up a condition in the situation event to send the event when the sales average dips below $100.
Answer: A
QUESTION 3
After running a simulation, a business analyst examines the Activity resource allocation analysis report produced by Modeler. In this report, no values are displayed. What causes the report to have no values?
A. There is not enough resource allocated to run simulation. B. Bulk resource is allocated during the simulation.
C. The simulation was run without resource requirements.
D. Resource Pool is not selected prior to simulation.
Answer: C
QUESTION 4
A manufacturing company has modeled the manufacturing process for all of their products under the jurisdiction of the planning department. The models are complete and the planning department is confident that most costs and
requirements have been included in the models. An accountant has approached the planning department and asked for a complete list of all production tooling
(machines, dies, etc.) and corresponding costs. The planning departments should respond by doing which of the following?
A. Refer the accountant to the IT department who should build a database of all tooling resources and what they are used for.
B. Report that the Modeling tools sole purpose is to model manufacturing process and data pulled from the models would be inaccurate and non-reliable.
C. Provide a report generated from a pre-defined query in Modeler called Resource
Specification.
D. Assign a business analyst to develop a custom query in Modeler to list resources and their corresponding costs.
Answer: C
QUESTION 5
Which of the following BEST characterizes a ‘reliable measure’?
A. It fulfills its purpose and resists contamination. B. It is not affected by sample size.
C. It produces the same result every time, given the same circumstances.
D. It produces the same result every time, regardless of the circumstances. Answer: C
QUESTION 6
Which of the following reports displays activities that have the longest duration among parallel paths after running a simulation against a process model?
A. Process instance activities free float report
B. Activity duration report
C. Process instance time report
D. Process instance critical path report
E. Process instance shortest path report
Answer: D
QUESTION 7
Each task in the process has the same processing time. Each task is accomplished with the same individual resource. In the Save Records task, the time required of
the resource exceeds the processing time. In the Update Information task, the resources time required equals the processing time. Given the simulation results, which two of the following measures remain constant during the running of the process simulation?
Exhibit:
A. Allocation duration
B. Elapsed duration
C. Delay duration
D. Shortage duration
E. Working duration
Answer: A,E
QUESTION 8
In order to establish CVS (Concurrent Versions System) Server as a repository for
WebSphere Business Modeler, which of the following must be performed?
A. A repository location is added in Preferences.
B. A CVS client is installed and configured with information provided by the CVS Administrator, and then Modeler is configured to use the CVS client in Preferences.
# Pass4sure ibm 000-990 Questions and Answers : 128 Q&A
# Updated: October 2nd , 2008
# Price: $159.99 $99.99
Free down:Testking ibm 000-990
Free down:Pass4sure ibm 000-990
| IBM Free Downloads |
|
Type |
Exam Bible | New Questions & Answers |
Latest Updated |
Download link |
![]() |
All Ibm 's Exam Pack |
767 |
1 days ago | Download |
If you would like to make a comment, please fill out the form below.
[...] Business Process Analyst: Business Process Analyst pass4sure 000-990 Exam : IBM WebSphere Business Modeler Advanced V6.0 , Business Analysis and [...]
[...] Business Process Analyst: Business Process Analyst pass4sure 000-990 Exam : IBM WebSphere Business Modeler Advanced V6.0 , Business Analysis and [...]